Management of temporary works on site

Our guide to loss prevention provides guidance on what Construction Site Managers need to know when installing temporary works for permanent basement and underpinning works. 
Construction Design and Management (CDM) 2015 All construction projects must operate in line with CDM 2015 regulations (replacing CDM 2007).

The regulations provide clear instruction on how construction projects must be run and what criteria makes a project notifiable. The regulations are bound in law and impositions can be imposed for breaching the regulations in the form of fines and prison sentences.

The regulations provide a clear understanding of the roles and responsibilities of each stakeholder and form a guide as to how temporary works must be managed to ensure the safe execution of high risk works including basement and underpinning works.

Download a copy of this document to access the full guidance from HSB. 

 

About HSB

HSB’s specialist underwriting in the UK and Ireland covers a broad range of risks including construction, cyber, computer, equipment breakdown and energy efficiency.

Built on a foundation of specialist insurance, engineering and technology, HSB is a global provider with over 150 years of technical risk knowledge and experience that sets the standard for excellence worldwide. Part of Munich Re, HSB is rated A++ (Superior) by A.M. Best Company.

Further information can be found at: www.hsbeil.com

Disclaimer:

*The guidance in this document refers to industry best practice loss control advice. Adoption of the advice contained within this document does not imply compliance with industry, statutory or HSB guidelines, nor does it guarantee that losses will not occur.

For more information, please contact us